Phase 1 of thetrevproject is complete – well sort of.

We are feeling quite bullish about our project at the moment.

 

This week we discovered  nice wooden floor in the living room which was a nice surprise. We were expecting to find a chipboard floor like the one in the new kitchen when we removed the old carpet. The fact that we found it is an indicator of progress, it means we are starting clear up.

We were promised that phase 1 would be complete by the end of September. Well it is  and it isn’t. Today the 2nd of October we have 2 builders on site clearing up and phase 1 is sort of finished.

Just a reminder about phase 1 and 2. The house is “L” shaped and phase 1 is the major part of the work which is the foot of the L. Phase 1 involved renovating 3 bedrooms, 2 reception rooms and an ensuite as well as the creation of a new downstairs loo. Oh and the repair of 5 sash window (listed building consent requirement) and the small matter of some major steel work to run alongside rotting or wood worm infested beams (again listed building consent requirement).

So where are we:-

Structural work – completed

New ensuite almost there – we just need a drain in the basin

Bedrooms complete – just need decorating and windows

New kitchen – complete apart from commissioning of range cooker booked for Friday

Downstairs loo – complete apart from extract fan

Windows – all still outstanding

 

The plan is, plumbers come today,  we get the first 2 windows back on Wednesday, cleaners come in Thursday and we move in Friday – that will be only a week behind target.

So we completed on time, well sort of yes, but really no. We still have to render two outside walls and we took most of the decorating out of the spec. This is an old house built with mud as mortar in one of the wettest parts of the UK only about 2.5 miles from the sea so we plan to leave the walls bare and dry the house out, once the heating is commissioned on Friday, for several months before we apply paint etc.

As a taster for what we are looking at there is a short video tour of the kitchen here (this video is unedited and one take so forgive the quality please):-

Also this week I have made progress with the slug barrier in the veg patch by almost completing a hard core path around 2 sides of the veg patch and laid some turf in the entrance from the road.

Phase 2 doesn’t need much in the way of structural work (so far as we know) so it will hopefully be a bit quicker than the first phase. Lets hope so we would like to be builder free by Christmas.

 

 

Advertisements

September at thetrevproject

Half way through September and this is the first update. Things are getting exciting now as the end of phase 1 is in sight. Just as well really as the stress and the dust and the dirt and the mess are starting to take their toll. Its amazing how you can get used to living in a tip – well not for me as I have always been pretty untidy. I was punished weekly at boarding school for not having a tidy bed and drawers etc for about 3 years. No one say I am not a quick learner  😆 – its just my definition of tidy was not the same as others.

Added to the stress is that our youngest daughter is home and she has to use a dark depressing bedroom and has no space to get her stuff out to make it homely. We are used to the lifestyle but it is hard for her to adapt.

The weather hasn’t helped either. Rain, rain, rain, admittedly interspersed with brief glimpses of the sun and a few lovely rainbows. Its been so wet that there is still standing corn around because its not been dry long enough to get the combines out. I have put the sun loungers away virtually unused this year. Last year October and November were great weatherwise, so here’s hoping. We have had a good couple of days weatherwise so Esme is getting a good end to her Cornish interlude, and guess what we did yesterday, The Eden Project – Thanks to Tesco Club Card we paid no cash to get in.

There is light at the end of the tunnel though. We have lights and electricity in the whole house at the moment. As of last week the electricians worked out what circuit was connected to which lights and transferred the circuits in phase 1 to a new breaker box. We have safe electrics in half the house now. Still a few minor modifications to make but we have progress. A slight challenge is we don’t have enough light bulbs to turn on all the lights at once. As we had so few lights working we didn’t bother buying many spares so we need to get some in. We still don’t have all the power sockets live but the circuits re connected.

These are the views from the windows in phase 1 at the moment – note the light bulbs in the two bedroom windows. May seem insignificant but when you have had no electricity for several months this quite a big deal. Oh, and that is not frosted glass in the bathroom it is cobwebs on the outside of the window.

We are having the radiators fitted this week and hopefully the Heritage Cooker/Boiler will be commissioned the following week. Just in time as the evenings draw in and start to get a little chilly. In the meantime I have to start moving dry wood to woodstore near the house and moving the logs outside into the shed to replace the dry logs removed.

Bank Holiday update 2

Lots going on in the house at present but the visuals are not that great so I thought I would start with a picture of our nearest beach since it is still Bank Holiday week. Lantic Bay is 5 minutes in the car and a short walk and on Bank Holiday Monday it was stunning see below.

The previous time we went to the beach there was one other person on the beach (sun was not shining).The downside is the 300 odd steps back up the cliff on the way out.

Also thought I would show some of our new neighbours – we are surrounded by pasture.

Well it’s a story of 2 fireplaces to tell. First the one in what will be our bedroom which is going to be blocked up. You can see it needed a bit of a sweep. The hearth is so small I don’t know what use is ever was.

The second is the fireplace in the living room which was about 45cm by 60 cm. We opened it up and found not one but two more fireplaces behind it. There’s work to be done here.

Some progress in the ensuite now. We are ready for the plumbing with floor and wall tiles installed. Electric first fix done.

We have also lost two windows – how careless.  🤣🤣 They are sash windows and have been removed to be taken away to be repaired. Its a listed building consent requirement, we cannot replace only repair. They are due back the end of the second week in September when the next 3 will be removed.

Thinking back, do you remember the cottage?

Well we have done some work in there as well. The Kitchen splash back has been ordered and partly installed. (ran out of tiles and Topps Tiles only had 2 in stock!).

Coming up next week.

Kitchen work top fitting

and hopefully radiators

book the cooker commissioning.

plus who knows what

Late July update from thetrevproject

So what has happened recently. Well….

The Lions drew a test series in New Zealand

England won the World Cup (women’s cricket)

Chris Froome won a 4th Tour de France – will he make into Sports Personality of the Year, probably not.

Oh yeah and what has happened to the Trev Project?

We have a load more stuff in the house as Josh and I went up to Widnes, hired a large van and brought all their stuff back to Trev. Most of it went in the garage but we are certainly very short of space now.  We now have 4 adults and 2 eleven month old twins living in half a house with only one temperamental toilet and a single bath. Its fun but I hope we get some more space soon.

Good news is that some stuff has moved out of the garage – the kitchen for Marler Cottage ready for fitting  so it was moved into the cottage and we could shoe horn Church Street Widnes in to the garage. Yes that means we are starting to put things back together again. The kitchen is going in the walls are painted, we have door and we have ordered an oil tank. We won’t make the completion by the end of July but we are hoping that a week into August the cottage will be habitable.

In the main house we have a floor in bedrooms 2 and 3. The floor is nice new pine, we looked at reclaimed floorboards but they were too expensive and we couldn’t find enough any way. The boards were kept in the room for  a week to acclimatise before being used. I did not realise how much work is involved laying a floor. Every board has to be racheted into place to ensure a tight fit and clasp nails hammered in by hand, no nail guns. There was the odd expletive from builders as they hammered fingers.

The walls are plastered  in the ensuite and we have a nice heritage roof lite in there. Tiles have been ordered for the floor and we are getting ready for the walls to be skimmed.

Downstairs the kitchen walls are ready for skimming. The walls are ready for skimming and the first floor tiles have gone in ready for the Heritage Cooker to be installed on Wednesday.

In between all this I have been helping to remove the Maiden Bells of St Veep Church for repair. These bells are unique – we believe the only Virgin Peel in the country and possible the World. A Virgin Peel, in case you don’t know and I certainly didn’t, means the bells were cast and never tuned, they just had perfect pitch straight away. So all 6 bells were perfect pitch. There are many other maiden bells but no virgin peels.

The Trev Project First week in July

This is the beginning of July update. It’s a bit late but here is the first week of July update any way.

After a quiet week last week some visible progress this week despite the rain.

First of all the heritage roof light went in to the cottage on Monday. What you may ask is a heritage roof light – well basically an expensive one that is supposed to look in keeping with the period of construction. It was specified due to the Grade II listing but why we needed a special one who knows. It is incredibly heavy so we do get something for our money  and it does look very good.  It goes in the kitchen which is in the middle of the cottage and gives a nice lot of light in the middle of the building.

Unfortunately on Tuesday the heavens opened and the roofers disappeared. We couldn’t open up the roof while it was pouring with rain.

We installed the 4th window as well and the internal sills were installed on all of them. We were therefore able to finish the internal insulation and plaster board and we are ready for plastering . Then we are able to get on to finishing  – well we still need glass in the windows and the handles etc.

We have ordered the floor tiles as well for install after the plastering is complete.

In the main house we made the decision to go for new floor boards. There were not enough reclaim boards around  and we need to make progress. We have bent over back wards and further to preserve joists and beams despite the fact it would be cheaper and easier to have replaced the lot. There is still a lot of rotten wood worm riven timber in place. It has all been treated but rot is a fungus and spores are notoriously difficult to kill so you can’t be sure it won’t recur at some point. We just have to try and avoid damp conditions (see and earlier post) and hope we are ok. The picture below is the new floorboards acclimatising – they need to be stored for about a week in the place where they are to be installed to prevent shrinkage or expansion etc.

The structure in bedroom 1 & 2 complete we turned our eyes to bedroom 1. Visually much less rotten but a nice surprise awaited. The wooden lintel above the living room was totally rotten – see picture below. We were already going to install a steel to support the window but now we have to install a second concrete lintel to replace the rotten wooden one. You can see below the very rotten one which should have been as big as the slightly rotten one next to it.

The pictures below are a bit dark but you can see the supports and steel work required to keep the living room ceiling together while the steel reinforcement is installed

 

Another big step forward was the arrival of electricians for the first fix in the main house. This is all the underfloor wiring in phase 1 (the foot of the “L” i.e. bedroom 1,2, & 3 ensuite lounge and new kitchen) off the repair. This is anticipation of new floor boards being laid in the next week.

The collateral from this is that we are very short of space for storing things and our kitchen is taking up a lot of space in the hall way.  This makes it very difficult to check the new kitchen which has arrived but we have identified that a sink is missing so there is a lot of backwards and forwards going on to find out why and where etc.

Another big change is that we have more residents now. Kate and Josh have arrived with the twins so we have even less room for storage. They have only brought one car load of stuff with them and we will collect their belongings in a few weeks.

Also there is a bat house update – the swallows have moved in and the chicks are doing well. I reckon these little beauties are worth about £1000.00 each!!!

Installing New Steel to Reinforce the rotten Wood @ TheTrevProject

Installing New Steel to Reinforce the rotten Wood

Since our last update there has been some significant progress although we are now in a bit of a hiatus. Due to illness etc. we are down to one builder on site the last couple of days.  We have been blessed with some fantastic weather with Britain (but not Cornwall) officially making it to heat wave status. We had the hottest summer day since 1976 at 35.6°C – hot by British standards but places like Singapore get that temperature about 7 months a year.

First major issue was to do the preparation for the installation of the structural steel. Basically we are a listed building so we are obliged to keep a much old structure as possible. In our case we have to keep some old joists and an old beam. The beam is severely rotted and damaged by woodworm etc.  So we have to fit steel beams either side of the main beam and bolt all of them together. The beam is approx. 300mm x 200mm, or at least it should be. In reality some of it is only 60% of that size. Surprisingly though the middle of the beam is still incredibly hard. It made it very difficult to drill a hole through the beam to fit large threaded rod between the steels.

So we lifted the steels up through the window.

     

We then had to clear the area where the steel was to be anchored and install a steel I beam lintel in the outer wall. The inner wall had to be hollowed out and a hard pocket installed to rest the steel on. To do this the ends of all the joists had to cut off. They were pretty rotten any way so it was a good move. But then as part of the LBC (Listed Building Consent) we had to retain the old joists and bolt a new one alongside each old one! This meant chiseling out a pocket in the inner beam as well.

Having done that the joists on the other side of the beam had to be cut and a steel place on the other side of the beam. Straight forward as we had already done it once. The difficulty was drilling a hole from one side of the beam through to the other side to tie the two steels and the wooden beam together. As the drill started in soft semi degraded wood and then hit rock hard oak in the middle it was kicked off of straight meaning it came out 10 – 20 mm off straight on the other side so it didn’t line up with the hole in the steel.

We had to put new joists alongside some every bent originals as you can see from the photo below. You can see also that some joists have been repaired up to 3 times before.

Then we discovered that there were issues on the wall side. A couple of joists were totally rotten so they had to be discarded.

 

The other issue was that some of the joists rested on a wooden lintel – which of course was rotten. With some well judged stone work we overcame the issues.

We are now ready to install floorboards in bedroom 2 and 3 but not bedroom 1 were we still have some steel work to install. Since we are an old listed building we have to try to install reclaimed floorboards. We have saved some but many of the floorboards removed were so rotten and riddled with wood worm that we had to burn them.

We also discovered that we have been very lucky not to have been burned down. There were numerous dead mice (desiccated) under the floor boards when we lifted the floor. We have now discovered that in a lot of places the mice had chewed the plastic insulation away and there were bare wires in several places.

 

Whilst this was going on the plumber arrived. He removed the old boiler (second-hand in 2014 and it was in excess of 20 years old), disconnected and drained the heating. A new element was installed in the hot water tank so we can be sure of hot water. We also removed several radiators.

 

Mid June Building Update TheTrevProject

Building Update at TheTrevProject

We have had a lot going on in the last couple of weeks since the last update – at least that is what the stage payment request tells me. There isn’t much visual to report on though but that might change for next week’s update.

So up to the beginning of this week we had the walls in the cottage completely insulated and they are basically ready for plastering now. You can see Alfie checking out the cladding below.

We finally got a response to our structural queries (to be fair Peter was on holiday and we did get a response from him so that is quite good). So the concrete lintel was removed from the cottage and a steel one installed higher up so we can now fit in our bifold doors.

  

We also have an answer to structural issues in the main house so that work is progressing as I write. Lost more to report on that next week.

Another step forward is the erection of scaffolding for the “heritage conservation roof light windows”. Basically expensive Velux type windows for the cottage kitchen and ensuite bathroom.

What has been highlighted though is how much lighter and more airy our front entrance is now. Below are two pictures showing the current light open access compared to the overgrown dark oppressive access in 2015 (we had already done quite a bit of cutting back of plant life when the photo was taken). Quite apart from the darkness all the vegetation is not good for the walls as it encourages damp. The dead leaves also block gutters which leads to damp and even wall collapse.

You can see also that the vegetation has been massively reduced by looking back into the building.